Good project management is very important with virtual teams.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity D? A)  32 days B)  41 days C)  44 days D)  42 days E)  40 days What is the estimated expected (mean) time for activity D?


A) 32 days
B) 41 days
C) 44 days
D) 42 days
E) 40 days

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

Shortening activity durations is called:


A) expediting.
B) crashing.
C) vendor management.
D) null nodes.
E) trade-off analysis.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following stages is that one in which the project's expected costs, benefits, and risks are assessed?


A) executing
B) monitoring/controlling
C) assessment
D) planning
E) initiating

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

A sequence of activities that leads from the starting node to the finishing node is called a:


A) path.
B) sequel.
C) trail.
D) critical sequence.
E) time line.

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Although PERT and CPM were originally developed independently, they are now nearly identical in terms of analysis and procedures.

A) True
B) False

Correct Answer

verifed

verified

One upside to terminating a project that is not going as well as planned is that:


A) poorly performing project team members will be kept from causing trouble elsewhere.
B) no additional costs will be incurred.
C) poor project managers will be weeded out.
D) resources can perhaps be put to better use elsewherE.
E) project completion will be hastened.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

In project network analysis, "slack" refers to the difference between:


A) observed and predicted times.
B) optimistic and pessimistic times.
C) mean and modal times.
D) finish and start times.
E) latest and earliest times.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a form of risk reduction in project management?


A) backup system
B) outsourcing
C) risk sharing
D) scenario analysis
E) frequent monitoring of critical project dimensions in order to catch and eliminate problems early

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?


A) expected project duration
B) activity slack time
C) which activities are on the critical path
D) variance in project duration
E) maximum project duration

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

The sum of times of the longest path in a network indicates expected project duration, and the activities represent the critical activities.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not an element of the project management triangle?


A) cost
B) schedule
C) resources
D) quality
E) performance objectives

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Showing 101 - 113 of 113