Filters
Question type

Study Flashcards

Differences between actual costs and standard costs are known as ___________________.These differences may be subdivided into _________________ and _________________.

Correct Answer

verifed

verified

cost variances; pric...

View Answer

Based on predicted production of 25,000 units,Best Co.anticipates $175,000 of fixed costs and $137,500 of variable costs.What are the flexible budget amounts of total costs for 20,000 and 30,000 units?

Correct Answer

verifed

verified

Variable costs = $137,500/25,0...

View Answer

A cost variance is the difference between actual cost and standard cost.

A) True
B) False

Correct Answer

verifed

verified

______________________ are preset costs for delivering a product or service under normal conditions.

Correct Answer

verifed

verified

Reference: 21_09 This information comes from the records of Dina Co. for the current period: Reference: 21_09 This information comes from the records of Dina Co. for the current period:    Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25/direct labor hour Fixed overhead $1.95/direct labor hour -Make the necessary general journal entries to record the above standard and actual costs,and all variances. Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25/direct labor hour Fixed overhead $1.95/direct labor hour -Make the necessary general journal entries to record the above standard and actual costs,and all variances.

Correct Answer

verifed

verified

blured image_TB6312_00...

View Answer

Use the following data to find the direct labor efficiency variance.  Direct labor standard (4 hrs. @  $28 per unit  $7/hr.)   Actual hours worked per unit  3.5 hours  Actual units produced 3,500 units  Actual rate per hour $7.50\begin{array}{ll}\text { Direct labor standard (4 hrs. @ } & \text { \$28 per unit } \\\text { \$7/hr.) } & \\\text { Actual hours worked per unit } & \text { 3.5 hours } \\\text { Actual units produced } & 3,500 \text { units } \\\text { Actual rate per hour } & \$ 7.50\end{array}


A) $6,125 unfavorable
B) $7,000 unfavorable
C) $7,000 favorable
D) $12,250 favorable
E) $6,125 favorable

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

The difference between the actual sales and the flexible budget sales is called the ______________________ variance.

Correct Answer

verifed

verified

sales pric...

View Answer

If actual price per unit of materials is greater than the standard price per unit of materials,the direct materials price variance is _______________________.

Correct Answer

verifed

verified

The difference between actual and standard cost caused by the difference between the actual price and the standard price is called the:


A) Standard variance.
B) Quantity variance.
C) Volume variance.
D) Controllable variance.
E) Price variance.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Reference: 21_04 A company has established 5 pounds of Material M at $2 per pound as the standard for the material in its Product A. The company has just produced 1,000 units of this product, using 5,200 pounds of Material M that cost $9,880. -The direct materials quantity variance is:


A) $400 unfavorable
B) $120 favorable
C) $400 favorable
D) $520 favorable
E) $520 unfavorable

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Briefly describe the procedure of management by exception.

Correct Answer

verifed

verified

Management by exception is an analytical...

View Answer

Define standard costs.How do they assist management?

Correct Answer

verifed

verified

Standard costs are preset costs for deli...

View Answer

Reference: 21_05 A job was budgeted to require three hours of labor per unit at $8 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. -What is the total labor cost variance?


A) $22,000 unfavorable
B) $16,000 unfavorable
C) $6,000 unfavorable
D) $16,000 favorable
E) $22,000 favorable

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

Reference: 21_03 Bradford Company budgeted 4,000 pounds of material costing $5 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. -What is the direct materials quantity variance?


A) $400 unfavorable
B) $450 unfavorable
C) $2,500 unfavorable
D) $2,550 unfavorable
E) $2,950 unfavorable

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

A company had a $22,000 favorable direct labor efficiency variance during a time period when the standard rate per direct labor hour was $22 and the actual rate per direct labor hour was $21.If the standard direct labor hours allowed for production were 5,000 what is the amount of actual direct labor cost during this period?


A) $84,000
B) $88,000
C) $100,000
D) $105,000
E) $110,000

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

Should both favorable and unfavorable variances be investigated,or only the unfavorable ones? Explain.

Correct Answer

verifed

verified

Any significant variance,whether favorab...

View Answer

When standard manufacturing costs are recorded in the accounts and the cost variances are immaterial at the end of the accounting period,the cost variances should be:


A) Carried forward to the next accounting period.
B) Allocated between cost of goods sold, finished goods, and goods in process.
C) Closed to cost of goods sold.
D) Written off as a selling expense.
E) Ignored.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Reference: 21_06 The following information describes a company's use of direct labor in a recent period:  Actual hours used45,000 Actual rate per hour$15 Standard rate per hour$14 Standard hours for units produced47,000\begin{array}{llr} \text { Actual hours used} &45,000\\ \text { Actual rate per hour} &\$15\\ \text { Standard rate per hour} &\$14\\ \text { Standard hours for units produced} &47,000\\\end{array} -The direct labor efficiency variance is:


A) $28,000 unfavorable
B) $28,000 favorable
C) $45,000 unfavorable
D) $45,000 favorable
E) $17,000 unfavorable

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

A company had a $22,000 favorable direct labor efficiency variance during a time period when the standard rate per direct labor hour was $22 and the actual rate per direct labor hour was $21.If the standard direct labor hours allowed for production were 5,000,what is the amount of actual direct labor hours worked during this period?


A) 6,000 hours
B) 4,000 hours
C) 88,000 hours
D) 110,000 hours
E) 22,000 hours

F) A) and D)
G) A) and B)

Correct Answer

verifed

verified

Standard costs can serve as a basis for evaluating actual performance.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 179

Related Exams

Show Answer